Today the guys started at 6:30 in the AM and left at 8:30 PM....In that time they were able to hang all the rafters and install the subfloor for the third floor. They also hoisted the beams over the living room into place.......So far so good, we like the flow of the rooms on both the first and second floors, one more floor to go.....
From March of 2005-July of 2006 we built a new house on an urban infill lot near downtown Sacramento. Jeff designed it, Mike was the general contractor. Our house is 3 stories high and 17' wide x 72' long. Among the goals were energy efficiency, cool design, & noise mitigation as we are right next to a 10 lane freeway. The house has solar electric, solar hot water & radiant heat. For the past 9 years we have been working on the landscaping and enjoying our home.