Week 1 results

Footings Dug - Check
Forms Installed - Check
Plumber - pipes under slab - Check
Electrical - conduit under slab - Check
Gas - Pipe under slab - Check
Tie Downs - `Gee sorry guys, I was delayed' - (Welcome to the world of contractor drama.)
First building inspection by city - `You have no Tie Downs installed' - try again next week.

Monday April 25th was to be the day the footings were poured...That is now delayed.....

Comments

Popular posts from this blog

Out of the gutter and into the cold..

Although the stucco guys completed their job a couple of weeks ago, some minor cracks developed in 3 areas and they have come back to patch them up..... Having the scaffold up for the stucco guys allowed our gutter guy to hang the final piece.... On Wednesday of this week the guys from Airsmiths installed the air conditioning condenser...If you're wondering if that is the American Standard Allegiance 14 Super Efficiency Condenser, you would be right! It is made in Texas in the same factory that Trane air conditioners are made at. http://www.americanstandardair.com/Products.asp?Section=homeOwners&ProductID=7&CategoryID=16&SuperCategoryID=1

Controlling the weather

We installed a Weathermatic irrigation system controller.  It is connected to an on-site weather station that monitors temperature, rainfall, windspeed, and humidity. As the seasons change, it automatically adjusts the station timing, very handy! UPDATE:  We had nothing but trouble with this controller and in 2016 we replaced it with a dramatically better one from Rachio. See it here: https://www.rachio.com/ Better yet, the City of Sacramento has a rebate program to replace old controllers with `smart' controllers like the Rachio, check it out here: https://www.cityofsacramento.org/Utilities/Conservation/Rebates/River-Friendly-Landscape-Rebate  

Electricity is done!

Our electrical service is done! (well, except for the all important punch list that will be knocked out on Monday) The Integrity Electic guys spent several days here this week. They said we have one of the most intense switching systems they have ever seen in a residential project.......I must confess that I'm still not sure what all 12 of the switches behind the front door actually do..... Pictured is Joe from Integrity Electric putting the finishing touches on our kitchen island. The counter top guys were here on Wed to measure the counters, they were fabricated today and will be installed next Wednesday....