Final-ly

The electrician was here most of Saturday, the plumber was here most of the morning today, the HVAC guys are still here.....The punch list from Friday was punched out.....

The inspector came by....

The final signature is on the dotted line...

We have officially passed the last major hurdle....

We have some trim work to finish this week, some countertop needs to be installed in the laundry area, there are 3 more doors to hang...when that is all done, we'll call the painters and hopefully by the end of next week the place will be pretty much DONE....

Comments

Popular posts from this blog

Out of the gutter and into the cold..

Although the stucco guys completed their job a couple of weeks ago, some minor cracks developed in 3 areas and they have come back to patch them up..... Having the scaffold up for the stucco guys allowed our gutter guy to hang the final piece.... On Wednesday of this week the guys from Airsmiths installed the air conditioning condenser...If you're wondering if that is the American Standard Allegiance 14 Super Efficiency Condenser, you would be right! It is made in Texas in the same factory that Trane air conditioners are made at. http://www.americanstandardair.com/Products.asp?Section=homeOwners&ProductID=7&CategoryID=16&SuperCategoryID=1

Controlling the weather

We installed a Weathermatic irrigation system controller.  It is connected to an on-site weather station that monitors temperature, rainfall, windspeed, and humidity. As the seasons change, it automatically adjusts the station timing, very handy! UPDATE:  We had nothing but trouble with this controller and in 2016 we replaced it with a dramatically better one from Rachio. See it here: https://www.rachio.com/ Better yet, the City of Sacramento has a rebate program to replace old controllers with `smart' controllers like the Rachio, check it out here: https://www.cityofsacramento.org/Utilities/Conservation/Rebates/River-Friendly-Landscape-Rebate  

We have officially started!

After almost 3 years of planning and designing on paper, today we took the first steps on the site of our new house. We cut down and carted away our fruit cocktail tree (a grafted fruit tree that had branches of nectarine, peach, plum, and apricot), 2 grape vines, a grafted Asian pear tree that had 4 varieties of pear, a grapefruit tree, a lemon tree, and an orange tree. It was sad to see them go, but it was exciting to think of what is to come.